Posted on: July 6, 2018

Central Ave Reconstruction - Phase 1 Information

DODGE CITY, Kansas. — The City of Dodge City’s Central Ave Reconstruction project is scheduled to start Monday, July 9, 2018. This project will be divided in to various phases of construction.

Phase 1 of the project will be to connect the new waterline to the existing waterline in the intersection of Central Ave. and Comanche St.  To accomplish this the intersection will be closed for approximately two weeks. Subsequent phases are approximately the length of one block and will take an estimated 2 months to complete the work for each phase.

“We plan to complete Phases 1 through 7 by mid-March, which will put us at Oak Street and the north side of Central Elementary,” said Ryan Scott, Construction Manager for Building Solutions. “Once we have completed through to Phase 7, we will shut down construction until school is out for the summer months.”

Central Ave. will be closed to through traffic where construction is taking place.  However during Phase 1; businesses along Central Ave will be accessible, and detour routes have been established.

“Due to the length of the project, media releases will be sent out periodically as work progresses with the phases,” said Abbey Martin, Public Information Specialist for the City of Dodge City. “The best way to get more frequent updates will be to follow the City on Facebook or subscribe to our weekly Community Newsletter through our website.”

A preliminary schedule is available to view, though keep in mind is subject to change. All phases of construction will consist of (in order):

•Setting up of traffic control to close the selected block(s) of Central Ave
•Removal of previously selected trees
•Removal of brick street, concrete sidewalks & driveways
•Excavation & installation of new sewer and water lines
•Placement of new subgrade
•Placement of new curb & gutter
•Placement of new driveways & sidewalks
•Placement of new street paving
For more information or questions please contact Building Solutions, LLC at (620) 225-1199 or City Of Dodge City Engineering department at (620) 225-8106.

Detour route for Phase 1.
•South Bound Traffic on Central Ave. wanting to go East on Comanche St.:
oTurn Left on W. La Mesa Dr.
oTake W. La Mesa Dr. to Ave. A.
oTake Ave. A to Comanche St.

•South Bound Traffic on Central Ave. wanting to go West on Comanche St.:
oTurn Right on Morgan Blvd.
oTake Morgan Blvd. to 1st Ave.
oTake 1st Ave. to Comanche St.

•North Bound Traffic on Central Ave. wanting to go East on Comanche St.:
oTurn Right on Magnolia St.
oTake Magnolia St. to Ave. A
oTake Ave. A to Comanche St.

•North Bound Traffic on Central Ave. wanting to go West on Comanche St.:
oTurn Left on Mulberry St.
oTake Mulberry St. to 2nd Ave.
oTake 2nd Ave. to Comanche St.

•North Bound Traffic on Central Ave. wanting to continue North on Central Ave.:
oTurn Right on Magnolia St.
oTake Magnolia St. to Ave. A
oTake Ave. A to Comanche St.
oContinue north on Ave. A to W. La Mesa Dr.
oTurn Left on W. La Mesa Dr.
oTake W. La Mesa Dr. to Central Ave.

•West Bound Traffic on Comanche St. wanting to go North on Central Ave.:
oTurn Right on Ave. A
oTake W. Ave. A. to W. La Mesa Dr.
oTurn left on W. La Mesa Dr.
oTake W. La Mesa Dr. to Central Ave.

•West Bound Traffic on Comanche St. wanting to go continue West on Comanche St.:
oTurn Right on Ave. A
oTake Ave. A. to W. La Mesa Dr.
oTurn left on W. La Mesa Dr.
oTake W. La Mesa Dr. to Central Ave.
oCross Central Ave. onto Morgan Blvd.
oTake Morgan Blvd. to 1st Ave.  
oTurn Left on 1st Ave.
oTake 1st Ave. to Comanche St.

•East Bound Traffic on Comanche St. wanting to go North on Central Ave.:
oTurn Left on 1st Ave.
oTake 1st Ave. to Morgan Blvd.
oTurn Right on Morgan Blvd.
oTake Morgan Blvd. to Central Ave.

•East Bound Traffic on Comanche St. wanting to continue East on Comanche St.:
oTurn Right on 1st Ave.
oTake 1st Ave. to Magnolia St.
oTurn Left on Magnolia St.
oTake Magnolia St. to Ave. A
oTurn Left on Ave. A
oTake Ave. A to Comanche St.


Phasing Plan

Facebook Twitter Google Plus Email

Other News in Home

Community Newsletter

Posted on: July 20, 2018

Dodge City Days 2018 Prep

Posted on: July 17, 2018

Community Newsletter

Posted on: July 13, 2018

Community Newsletter

Posted on: July 6, 2018

Community Newsletter

Posted on: June 29, 2018

Community Newsletter

Posted on: June 22, 2018

Video Tour of Dodge City

Posted on: March 29, 2018